FY2013 NDAA

H.R.4310: National Defense Authorization Act for Fiscal Year 2013

Latest Major Action: 1/2/2013 Signed by President.

Source: US Government Printing Office


SEC. 807. SENSE OF CONGRESS ON THE CONTINUING PROGRESS OF THE DEPARTMENT OF DEFENSE IN IMPLEMENTING ITS ITEM UNIQUE IDENTIFICATION INITIATIVE.

(a) FINDINGS.—Congress makes the following findings:

(1) In 2003, the Department of Defense initiated the Item Unique Identification (IUID) Initiative, which requires the marking and tracking of assets deployed throughout the Armed Forces or in the possession of Department contractors.

(2) The Initiative has the potential for realizing significant cost savings and improving the management of defense equipment and supplies throughout their lifecycle.

(3) The Initiative can help the Department combat the growing problem of counterfeit parts in the military supply chain.

(b) SENSE OF CONGRESS.—It is the sense of Congress—

(1) to support efforts by the Department of Defense to implement the Item Unique Identification Initiative;

(2) to support measures to verify contractor compliance with section 252.211–7003 (entitled ‘‘Item Identification and Valuation’’) of the Defense Supplement to the Federal Acquisition Regulation, on Unique Identification, which states that a unique identification equivalent recognized by the Department is required for certain acquisitions;

(3) to encourage the Armed Forces to adopt and implement Item Unique Identification actions and milestones; and

(4) to support investment of sufficient resources and continued training and leadership to enable the Department to capture meaningful data and optimize the benefits of the Item Unique Identification Initiative.

 


 

SEC. 833. CONTRACTOR RESPONSIBILITIES IN REGULATIONS RELATING TO DETECTION AND AVOIDANCE OF COUNTERFEIT ELECTRONIC PARTS.

Section 818(c)(2)(B) of the National Defense Authorization Act for Fiscal Year 2012 (Public Law 112-81; 125 Stat. 1493; 10 U.S.C. 2302 note) is amended to read as follows:

`(B) the cost of counterfeit electronic parts and suspect counterfeit electronic parts and the cost of rework or corrective action that may be required to remedy the use or inclusion of such parts are not allowable costs under Department contracts, unless–

`(i) the covered contractor has an operational system to detect and avoid counterfeit parts and suspect counterfeit electronic parts that has been reviewed and approved by the Department of Defense pursuant to subsection (e)(2)(B);

`(ii) the counterfeit electronic parts or suspect counterfeit electronic parts were provided to the contractor as Government property in accordance with part 45 of the Federal Acquisition Regulation; and

`(iii) the covered contractor provides timely notice to the Government pursuant to paragraph (4).’.

 


 

SEC. 1603. NATIONAL SECURITY STRATEGY FOR NATIONAL TECHNOLOGY AND INDUSTRIAL BASE.

‘‘The Secretary of Defense shall develop a national security strategy for the national technology and industrial base. Such strategy shall be based on a prioritized assessment of risks and challenges to the defense supply chain and shall ensure that the national technology and industrial base is capable of achieving the following national security objectives: …’’

[new paragraph added]

‘‘(10) Reducing, to the maximum extent practicable, the presence of counterfeit parts in the supply chain and the risk associated with such parts.’’


 